Phase & engagement timelines — relative duration & overlap
Design-Bid-Build (DBB)
Traditional linear sequence — design 100% complete before contractor is selected
Project phases
1. Planning
2. Design
3. Pre-con
4. Construction
5. CO
Owner
Engaged throughout
Designer / AE
Design & documentation
Contract admin / site observation
Contractor (GC)
Bid → Build → Closeout
Permitting
Entitlements
Plan check
Permit
Inspections → CO
Design-Build (DB)
Single entity responsible for both design and construction — significant phase compression and fast-tracking
Project phases
1. Planning
2. Design
3. Pre-con
4. Construction (fast-tracked)
5. CO
Owner
Engaged throughout — fewer design touchpoints mid-project
Designer / AE
Design progresses in parallel with construction (part of DB entity)
Contractor (GC)
Engaged at design start — leads DB entity
Permitting
Entitlements
Plan check (phased)
Grad.
Fnd.
Shell
Inspections → CO
Construction Manager at Risk (CMAR)
CM engaged during design as advisor; commits to Guaranteed Maximum Price (GMP) before construction
Project phases
1. Planning
2. Design
3. Pre-con
4. Construction (fast-tracked)
5. CO
Owner
Engaged throughout — retains design control via separate AE contract
Designer / AE
Full design services — contracted directly with owner
CM / Contractor
Pre-con: estimating, constructability, scheduling
GMP committed → Build → Closeout
Permitting
Entitlements
Plan check (phased)
Grad.
Fnd.
Shell
Inspections → CO
Key dimension comparison
| Dimension | Design-Bid-Build (DBB) | Design-Build (DB) | Construction Manager at Risk (CMAR) |
|---|---|---|---|
| Contractor selection timing | After design is 100% complete. Competitive low-bid or best-value selection. | Early — at or shortly after project programming. DB entity selected on qualifications + price. | During design (Phase 2). Selected on qualifications & fee; GMP negotiated at ~60–70% design. |
| Design completion at construction start | 100% Full construction documents issued for bid before any work begins. |
30–50% Early packages (site, foundation) begin while design continues in parallel. |
60–70% GMP set; phased packages released as design progresses. |
| Owner design control | High — Owner contracts directly with AE. Full control over design throughout. | Lower — Design is part of DB entity. Owner influence reduced post-contract. Requires strong bridging documents. | High — Owner retains direct AE contract. CM provides input but does not control design. |
| Cost certainty & risk allocation | Cost known only at bid. Post-bid changes are owner-funded change orders. | Lump sum set early — DB entity absorbs design development risk within contract price. | GMP = cost ceiling — Savings may be shared. Owner exposed above GMP for scope changes. |
| Schedule advantage | Slowest — Sequential phases. No construction until full design & bid complete. | Often fastest — Maximum phase compression. Favoured when schedule is the primary driver. | Moderate compression — Early CM allows long-lead procurement & phased permitting during design. |
| Long-lead procurement | Cannot begin until after bid award. Risk of escalation between design and procurement. | DB entity can procure long-lead items as design progresses — significant schedule & cost risk reduction. | CM can identify and procure long-lead items (switchgear, elevators, curtain wall) during pre-construction, before GMP is set. |
| Phased permitting approach | Typically single permit after 100% design. Phased permits possible but less common. | Phased permitting standard. Grading, foundation, shell permits issued in sequence as design packages complete. | Phased permitting common. CM coordinates permit sequencing with AE during pre-construction. |
| Typical best-fit project types | Public projects with prescriptive procurement rules. Straightforward scope. Budget-driven with adequate schedule. | Schedule-critical projects. Repetitive types (hotels, multifamily, warehouses, data centers). Strong owner performance-spec capability. | Complex institutional (hospitals, universities), large commercial, projects needing design quality with schedule compression. Often seen on projects over $50M. |
| Common sectors (from matrix) | Residential (all). Public institutional (many states require DBB for public funds). Small-to-mid commercial. | Industrial, warehouse, data centers, multifamily, hospitality. Growing use in heavy civil & public infrastructure. | Hospitals, K-12 & higher education, large office & mixed-use, airports, transit facilities. |